| TATA POWER - DDL Distribution System Outage Request From 16-Nov-2025 To 17-Dec-2025 |
| S. No |
Discom |
Distt |
Zone |
DESCRIPTION |
Date Time from |
Date Time to |
Area affected |
Total Duration (in Hrs) |
| 1 |
TATA POWER - DDL |
CIVIL LINES |
411 |
PREVENTIVE MAINTENANCE |
16.11.25 11:00 |
16.11.25 15:00 |
PART OF TIS HAZARI |
4 |
| 2 |
TATA POWER - DDL |
MANGOLPURI |
515 |
PREVENTIVE MAINTENANCE |
16.11.25 11:30 |
16.11.25 15:30 |
PART OF T BLK MIA |
4 |
| 3 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
17.11.25 06:00 |
17.11.25 09:00 |
PART OF L BLK SEC 3 |
3 |
| 4 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
17.11.25 07:30 |
17.11.25 09:30 |
PART OF E 638 TO E 663 |
2 |
| 5 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
17.11.25 09:30 |
17.11.25 12:30 |
PART OF SGTN |
3 |
| 6 |
TATA POWER - DDL |
CIVIL LINES |
411 |
PREVENTIVE MAINTENANCE |
17.11.25 10:30 |
17.11.25 12:30 |
PART OF UNDER HILL ROAD |
2 |
| 7 |
TATA POWER - DDL |
KESAHAVPURAM |
501 |
PREVENTIVE MAINTENANCE |
17.11.25 10:30 |
17.11.25 12:30 |
PART OF A BLOCK KESHAVPURAM |
2 |
| 8 |
TATA POWER - DDL |
MANGOLPURI |
515 |
PROJECT WORK |
17.11.25 10:30 |
17.11.25 12:30 |
PART OF G BLK MIA |
2 |
| 9 |
TATA POWER - DDL |
MODEL TOWN |
505 |
PREVENTIVE MAINTENANCE |
17.11.25 10:30 |
17.11.25 14:30 |
PART OF K-BLK 751 WALI GALI |
4 |
| 10 |
TATA POWER - DDL |
MODEL TOWN |
505 |
PREVENTIVE MAINTENANCE |
17.11.25 10:30 |
17.11.25 14:30 |
PART OF H-BLK JJ CLUSTER |
4 |
| 11 |
TATA POWER - DDL |
MOTI NAGAR |
1302 |
PREVENTIVE MAINTENANCE |
17.11.25 10:30 |
17.11.25 14:30 |
PART OF B BLK PHASE -2 |
4 |
| 12 |
TATA POWER - DDL |
MOTI NAGAR |
1303 |
PREVENTIVE MAINTENANCE |
17.11.25 10:30 |
17.11.25 12:30 |
PART OF TREE TRIMMING |
2 |
| 13 |
TATA POWER - DDL |
MOTI NAGAR |
1302 |
PREVENTIVE MAINTENANCE |
17.11.25 10:50 |
17.11.25 14:50 |
PART OF B BLK PHASE-2 NIA |
4 |
| 14 |
TATA POWER - DDL |
BADLI |
516 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF DEEP VIHAR |
4 |
| 15 |
TATA POWER - DDL |
BAWANA |
521 |
PROJECT WORK |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF POOTH VILL AND |
4 |
| 16 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF KANJHAWALA INDUSTRIAL AREA |
4 |
| 17 |
TATA POWER - DDL |
KIRARI |
513 |
PROJECT WORK |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF RAMA VIHAR |
4 |
| 18 |
TATA POWER - DDL |
KIRARI |
523 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF STATION BLOCK |
4 |
| 19 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 13:00 |
PART OF O&P BLOCK KRISHAN VIHAR |
2 |
| 20 |
TATA POWER - DDL |
MODEL TOWN |
402 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 13:00 |
PART OF ADARSH NAGAR |
2 |
| 21 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF ZINDPUR |
4 |
| 22 |
TATA POWER - DDL |
NARELA |
514 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF BANKNER VILLAGE |
4 |
| 23 |
TATA POWER - DDL |
NARELA |
517 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF SINGHOLA |
4 |
| 24 |
TATA POWER - DDL |
ROHINI |
581 |
PREVENTIVE MAINTENANCE |
17.11.25 11:00 |
17.11.25 15:00 |
PART OF BADLI VILLAGE |
4 |
| 25 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
17.11.25 12:00 |
17.11.25 16:00 |
PART OF PARVESH NAGAR |
4 |
| 26 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
17.11.25 12:00 |
17.11.25 16:00 |
PART OF RAJ PARK PARTIALY , HARIZEN BSTI PARTIALY |
4 |
| 27 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
17.11.25 12:30 |
17.11.25 16:30 |
PART OF EAST FRIENDS ENCLAVE PARTIALY AND BERI WALA BAGH. |
4 |
| 28 |
TATA POWER - DDL |
CIVIL LINES |
411 |
PREVENTIVE MAINTENANCE |
17.11.25 14:00 |
17.11.25 16:00 |
PART OF DMRC FLATS |
2 |
| 29 |
TATA POWER - DDL |
MOTI NAGAR |
1303 |
PREVENTIVE MAINTENANCE |
17.11.25 14:30 |
17.11.25 16:00 |
PART OF A BLOCK SUDERSHAN PARK |
2 |
| 30 |
TATA POWER - DDL |
PITAMPURA |
508 |
PREVENTIVE MAINTENANCE |
17.11.25 14:30 |
17.11.25 16:00 |
PART OF SACHDEVA PUBLIC SCHOOL |
2 |
| 31 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
18.11.25 06:00 |
18.11.25 09:00 |
PART OF B BLK SEC 4 DSIIDC BAWANA |
3 |
| 32 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
18.11.25 06:00 |
18.11.25 09:00 |
PART OF B BLK SEC 4 DSIIDC BAWANA |
3 |
| 33 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
18.11.25 07:30 |
18.11.25 09:30 |
PART OF E 887 TO E 919 |
2 |
| 34 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
18.11.25 10:00 |
18.11.25 13:00 |
PART OF JJ COLONY |
3 |
| 35 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 10:00 |
18.11.25 11:00 |
PART OF GHOGHA VILAGE |
1 |
| 36 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 10:00 |
18.11.25 11:00 |
PART OF LAMPUR VILLAGE |
1 |
| 37 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 10:00 |
18.11.25 11:00 |
PART OF NARELA MANDI RAILWAY ROAD |
1 |
| 38 |
TATA POWER - DDL |
BAWANA |
512 |
PREVENTIVE MAINTENANCE |
18.11.25 10:30 |
18.11.25 13:30 |
PART OF LAMBA PANA QUTUBGARH |
3 |
| 39 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
18.11.25 10:30 |
18.11.25 13:00 |
PART OF GHEVRA VILLAGE |
3 |
| 40 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
18.11.25 10:30 |
18.11.25 12:30 |
PART OF A BLK NEHRU VIHAR |
2 |
| 41 |
TATA POWER - DDL |
MODEL TOWN |
505 |
PREVENTIVE MAINTENANCE |
18.11.25 10:30 |
18.11.25 13:00 |
PART OF RAMGARH NO-2 HVDS |
3 |
| 42 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
18.11.25 10:30 |
18.11.25 14:30 |
PART OF A9 SECTION |
4 |
| 43 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 13:00 |
PART OF SAMAY PUR |
2 |
| 44 |
TATA POWER - DDL |
CIVIL LINES |
416 |
PROJECT WORK |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF GURMANDI |
4 |
| 45 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF SUKHBIR NAGAR |
4 |
| 46 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF GALI NO 6 JAIN NAGAR |
4 |
| 47 |
TATA POWER - DDL |
KIRARI |
523 |
PROJECT WORK |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF RAMESH ENCLAVE |
4 |
| 48 |
TATA POWER - DDL |
MANGOLPURI |
515 |
PROJECT WORK |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF D BLK MIA |
4 |
| 49 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 13:30 |
PART OF T BLK MIA |
2 |
| 50 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
18.11.25 11:00 |
18.11.25 12:00 |
PART OF SEC-22 ROHINI |
1 |
| 51 |
TATA POWER - DDL |
MODEL TOWN |
415 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 13:00 |
PART OF SUBZI MANDI |
2 |
| 52 |
TATA POWER - DDL |
MODEL TOWN |
415 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 13:00 |
PART OF SUBZI MANDI |
2 |
| 53 |
TATA POWER - DDL |
MODEL TOWN |
415 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 13:00 |
PART OF SUBZI MANDI |
2 |
| 54 |
TATA POWER - DDL |
MODEL TOWN |
505 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF C-BLK |
4 |
| 55 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 13:00 |
PART OF DCM |
2 |
| 56 |
TATA POWER - DDL |
NARELA |
514 |
PREVENTIVE MAINTENANCE |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF SWATANTER NAGAER |
4 |
| 57 |
TATA POWER - DDL |
SHALIMARBAGH |
503 |
PROJECT WORK |
18.11.25 11:00 |
18.11.25 15:00 |
PART OF MUKUNDPUR & JANTA VIHAR |
4 |
| 58 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
18.11.25 11:15 |
18.11.25 13:15 |
PART OF DCM |
2 |
| 59 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
18.11.25 12:00 |
18.11.25 14:00 |
PART OF P-4 BLK S. PURI PARTIALYPARTIALY AREA OF P-4 BLK SULTANPURI .5 |
2 |
| 60 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
18.11.25 12:00 |
18.11.25 14:00 |
PART OF O&P BLOCK KRISHAN VIHAR |
2 |
| 61 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 12:00 |
18.11.25 13:00 |
PART OF NARELA BAZAR |
1 |
| 62 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 12:00 |
18.11.25 13:00 |
PART OF SWATANTRA NAGAR A PART |
1 |
| 63 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 12:00 |
18.11.25 13:00 |
PART OF PUNJABI COLONY NARELA MANDI |
1 |
| 64 |
TATA POWER - DDL |
NARELA |
514 |
METERING WORK |
18.11.25 12:00 |
18.11.25 13:00 |
PART OF GHPGHA VILLAGE |
1 |
| 65 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF SAMAY PUR |
2 |
| 66 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF DUSIB FLAT |
2 |
| 67 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF H BLOCK JJ COLONY |
2 |
| 68 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF C BLK NEHRU VIHAR |
2 |
| 69 |
TATA POWER - DDL |
MODEL TOWN |
415 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF D' BLOCK SAUBZI MANDI |
2 |
| 70 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF DCM |
2 |
| 71 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
18.11.25 14:00 |
18.11.25 16:00 |
PART OF IBRAHIMPUR |
2 |
| 72 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
19.11.25 06:00 |
19.11.25 09:00 |
PART OF K BLK SEC 2 |
3 |
| 73 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
19.11.25 06:15 |
19.11.25 09:15 |
PART OF K BLK SEC 2 |
3 |
| 74 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 14:00 |
PART OF A BLOCK COLONY |
4 |
| 75 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 13:00 |
PART OF K BLOCK |
3 |
| 76 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 12:30 |
PART OF TRUCK PARKING |
2 |
| 77 |
TATA POWER - DDL |
KESAHAVPURAM |
501 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 14:30 |
PART OF OF C- BLOCK KESHAVPURAM |
4 |
| 78 |
TATA POWER - DDL |
MODEL TOWN |
505 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 13:00 |
PART OF RAMGARH NO-2 HVDS |
3 |
| 79 |
TATA POWER - DDL |
MOTI NAGAR |
1304 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 13:00 |
PART OF FORECAST PUSA |
3 |
| 80 |
TATA POWER - DDL |
NARELA |
522 |
PREVENTIVE MAINTENANCE |
19.11.25 10:30 |
19.11.25 14:30 |
PART OF A5 MARKET AND KV SCHOOL |
4 |
| 81 |
TATA POWER - DDL |
BAWANA |
521 |
PROJECT WORK |
19.11.25 11:00 |
19.11.25 15:00 |
PART OF POOTH KHURD VILLAGE |
4 |
| 82 |
TATA POWER - DDL |
KIRARI |
513 |
PROJECT WORK |
19.11.25 11:00 |
19.11.25 14:00 |
PART OF RAMA VIHAR |
3 |
| 83 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
19.11.25 11:00 |
19.11.25 15:00 |
PART OF SUKHBIR NAGAR |
4 |
| 84 |
TATA POWER - DDL |
KIRARI |
523 |
PREVENTIVE MAINTENANCE |
19.11.25 11:00 |
19.11.25 13:00 |
PART OF LMP BLOCK |
2 |
| 85 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
19.11.25 11:00 |
19.11.25 15:00 |
PART OF P-4 BLK S. [PURI PARTIALY |
4 |
| 86 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PREVENTIVE MAINTENANCE |
19.11.25 11:00 |
19.11.25 13:00 |
PART OF BUDH VIHAR |
2 |
| 87 |
TATA POWER - DDL |
MODEL TOWN |
402 |
PREVENTIVE MAINTENANCE |
19.11.25 11:00 |
19.11.25 14:00 |
PART OF GTK |
3 |
| 88 |
TATA POWER - DDL |
NARELA |
511 |
PROJECT WORK |
19.11.25 11:00 |
19.11.25 15:00 |
PART OF ZINDPUR VILLAGE |
4 |
| 89 |
TATA POWER - DDL |
NARELA |
514 |
PROJECT WORK |
19.11.25 11:00 |
19.11.25 15:00 |
PART OF SWATANTER NAGER |
4 |
| 90 |
TATA POWER - DDL |
KESAHAVPURAM |
502 |
PROJECT WORK |
19.11.25 11:30 |
19.11.25 15:30 |
PART OF WPIA |
4 |
| 91 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
19.11.25 14:00 |
19.11.25 16:00 |
PART OF JJ COLONY |
2 |
| 92 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
19.11.25 14:00 |
19.11.25 16:00 |
PART OF BD ESTATE |
2 |
| 93 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PREVENTIVE MAINTENANCE |
19.11.25 14:00 |
19.11.25 16:00 |
PART OF RAJEEV NAGAR |
2 |
| 94 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
19.11.25 14:00 |
19.11.25 16:00 |
PART OF SEC-22 ROHINI |
2 |
| 95 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
19.11.25 14:00 |
19.11.25 16:00 |
PART OF DDA STREET LIGHT |
2 |
| 96 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
19.11.25 14:30 |
19.11.25 16:00 |
PART OF A BLOCK |
2 |
| 97 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
20.11.25 06:00 |
20.11.25 09:00 |
PART OF E BLK SEC 2 |
3 |
| 98 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
20.11.25 10:30 |
20.11.25 12:30 |
PART OF WAZIRABAD |
2 |
| 99 |
TATA POWER - DDL |
MODEL TOWN |
505 |
PREVENTIVE MAINTENANCE |
20.11.25 10:30 |
20.11.25 13:00 |
PART OF E-BLK |
3 |
| 100 |
TATA POWER - DDL |
KIRARI |
513 |
PROJECT WORK |
20.11.25 11:00 |
20.11.25 15:00 |
PART OF MADANPUR |
4 |
| 101 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
20.11.25 11:00 |
20.11.25 15:00 |
PART OF P-1 SULTANPURI |
4 |
| 102 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PREVENTIVE MAINTENANCE |
20.11.25 11:00 |
20.11.25 15:00 |
PART OF PKT-8 SEC-21 ROHINI |
4 |
| 103 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PREVENTIVE MAINTENANCE |
20.11.25 11:00 |
20.11.25 15:00 |
PART OF POOTHKALAN HVDS |
4 |
| 104 |
TATA POWER - DDL |
MODEL TOWN |
402 |
PREVENTIVE MAINTENANCE |
20.11.25 11:00 |
20.11.25 13:00 |
PART OF MAHNEDRU |
2 |
| 105 |
TATA POWER - DDL |
NARELA |
514 |
PREVENTIVE MAINTENANCE |
20.11.25 11:00 |
20.11.25 15:00 |
PART OF SWT NAGAR |
4 |
| 106 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
20.11.25 11:00 |
20.11.25 13:00 |
PART OF SEC-3 |
2 |
| 107 |
TATA POWER - DDL |
KIRARI |
513 |
PROJECT WORK |
20.11.25 13:00 |
20.11.25 16:00 |
PART OF RAMA VIHAR |
3 |
| 108 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
20.11.25 14:00 |
20.11.25 16:00 |
PART OF SAMAY PUR |
2 |
| 109 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
20.11.25 14:00 |
20.11.25 16:00 |
PART OF SAMAY PUR |
2 |
| 110 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
20.11.25 14:00 |
20.11.25 16:00 |
PART OF 3 CAVALRY LINES |
2 |
| 111 |
TATA POWER - DDL |
MODEL TOWN |
402 |
PREVENTIVE MAINTENANCE |
20.11.25 14:00 |
20.11.25 16:00 |
PART OF MAHENDRU |
2 |
| 112 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
20.11.25 14:00 |
20.11.25 16:00 |
PART OF SEC-3 |
2 |
| 113 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
21.11.25 06:00 |
21.11.25 09:00 |
PART OF I BLK SEC 5 |
3 |
| 114 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
21.11.25 10:30 |
21.11.25 12:30 |
PART OF T TIBETAN CAMP |
2 |
| 115 |
TATA POWER - DDL |
KESAHAVPURAM |
502 |
PREVENTIVE MAINTENANCE |
21.11.25 10:30 |
21.11.25 12:30 |
PART OF WPIA |
2 |
| 116 |
TATA POWER - DDL |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
21.11.25 11:00 |
21.11.25 15:00 |
PART OF N BLOCK |
4 |
| 117 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
21.11.25 11:00 |
21.11.25 15:00 |
PART OF AGAR NAGAR |
4 |
| 118 |
TATA POWER - DDL |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
21.11.25 11:00 |
21.11.25 15:00 |
PART OF P1 SULTANPURI |
4 |
| 119 |
TATA POWER - DDL |
MANGOLPURI |
519 |
METERING WORK |
21.11.25 11:00 |
21.11.25 15:00 |
PART OF PKT-5 SEC-22 |
4 |
| 120 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
21.11.25 11:00 |
21.11.25 13:00 |
PART OF PARTIAL C-BLOCK AVANTIKA |
2 |
| 121 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
21.11.25 14:00 |
21.11.25 16:00 |
PART OF F SIGNATURE BRIDGE |
2 |
| 122 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
21.11.25 14:00 |
21.11.25 16:00 |
PART OF AVANTIKA SEC-1 |
2 |
| 123 |
TATA POWER - DDL |
BAWANA |
521 |
PROJECT WORK |
22.11.25 08:30 |
22.11.25 14:30 |
PART OF K & L BLK SEC 5 |
6 |
| 124 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
22.11.25 10:30 |
22.11.25 12:30 |
PART OF PROBYN ROAD |
2 |
| 125 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
22.11.25 11:00 |
22.11.25 13:00 |
PART OF SAMAY PUR |
2 |
| 126 |
TATA POWER - DDL |
BAWANA |
521 |
PREVENTIVE MAINTENANCE |
22.11.25 11:00 |
22.11.25 13:00 |
PART OF O,L AND H BLK SEC 3 |
2 |
| 127 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PREVENTIVE MAINTENANCE |
22.11.25 11:00 |
22.11.25 15:00 |
PART OF PKT-10 SEC-21 ROHINI |
4 |
| 128 |
TATA POWER - DDL |
NARELA |
511 |
PREVENTIVE MAINTENANCE |
22.11.25 11:00 |
22.11.25 15:00 |
PART OF KUSHAK NO-1 |
4 |
| 129 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
22.11.25 11:00 |
22.11.25 13:00 |
PART OF SEC-1 |
2 |
| 130 |
TATA POWER - DDL |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
22.11.25 14:00 |
22.11.25 16:00 |
PART OF SAMAY PUR |
2 |
| 131 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
22.11.25 14:00 |
22.11.25 16:00 |
PART OF MAURICE NAGAR |
2 |
| 132 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
22.11.25 14:00 |
22.11.25 16:00 |
PART OF SEC-1 |
2 |
| 133 |
TATA POWER - DDL |
KIRARI |
513 |
PROJECT WORK |
23.11.25 11:00 |
23.11.25 15:00 |
PART OF PKT C1 ESS 8 SEC-37 |
4 |
| 134 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
23.11.25 14:00 |
23.11.25 16:00 |
PART OF VIJAY VIHAR-2 |
2 |
| 135 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
24.11.25 10:30 |
24.11.25 12:30 |
PART OF BANTA SINGH |
2 |
| 136 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
24.11.25 11:00 |
24.11.25 15:00 |
PART OF VIDYAPATI NAGAR |
4 |
| 137 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
24.11.25 11:00 |
24.11.25 15:00 |
PART OF KRISHAN VIHAR NO-1 HVDS |
4 |
| 138 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
24.11.25 14:00 |
24.11.25 16:00 |
PART OF SINDHI BABA |
2 |
| 139 |
TATA POWER - DDL |
CIVIL LINES |
411 |
PREVENTIVE MAINTENANCE |
25.11.25 10:30 |
25.11.25 12:30 |
PART OF ALIPUR ROAD |
2 |
| 140 |
TATA POWER - DDL |
MANGOLPURI |
519 |
PROJECT WORK |
25.11.25 11:00 |
25.11.25 15:00 |
PART OF HARSHDEV PARK |
4 |
| 141 |
TATA POWER - DDL |
CIVIL LINES |
418 |
PREVENTIVE MAINTENANCE |
25.11.25 14:00 |
25.11.25 16:00 |
PART OF 3 CAVALRY LINES |
2 |
| 142 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
28.11.25 11:00 |
28.11.25 15:00 |
PART OF RANIKHERA |
4 |
| 143 |
TATA POWER - DDL |
ROHINI |
551 |
PREVENTIVE MAINTENANCE |
30.11.25 11:00 |
30.11.25 15:00 |
PART OF VIJAY VIHAR-2 |
4 |
| 144 |
TATA POWER - DDL |
KIRARI |
513 |
PREVENTIVE MAINTENANCE |
01.12.25 13:00 |
01.12.25 16:00 |
PART OF SUKHBIR NAGAR |
3 |
| 145 |
TATA POWER - DDL |
SHALIMARBAGH |
532 |
PREVENTIVE MAINTENANCE |
03.12.25 10:30 |
03.12.25 13:30 |
PART OF HARIZAN BASTI |
3 |