Maintenance Shutdown Schedule
The augmentation and maintenance work will be carried out in the areas mentioned below to ensure an uninterrupted power supply and no equipment failure / breakdown. Due to this, the Electricity supply may be affected in the following areas on
22/03/2023 |
S. No | Distt | Zone | DESCRIPTION | Date Time from | Date Time to | Area affected | Total Duration (in Hrs) |
1 |
BADLI |
507 |
PREVENTIVE MAINTENANCE |
22.03.23 10:00 |
22.03.23 16:00 |
PART OF SANAJY GANDHI |
6 |
400 |
4 |
BADLI |
516 |
PREVENTIVE MAINTENANCE |
22.03.23 10:00 |
22.03.23 16:00 |
A PART OF SEC-27 |
6 |
425 |
5 |
BAWANA |
533 |
PREVENTIVE MAINTENANCE |
22.03.23 10:30 |
22.03.23 16:00 |
PART OF NIZAMPUR |
6 |
400 |
6 |
CIVIL LINES |
423 |
PREVENTIVE MAINTENANCE |
22.03.23 10:30 |
22.03.23 12:30 |
A PART OF BARA DARI |
2 |
1200 |
7 |
KESAHAVPURAM |
501 |
PROJECT WORK |
22.03.23 08:00 |
22.03.23 16:00 |
PART OF INDL AREA |
8 |
35 |
8 |
KESAHAVPURAM |
502 |
PREVENTIVE MAINTENANCE |
22.03.23 10:30 |
22.03.23 12:30 |
PARTS OF WZPIA |
2 |
3 |
9 |
KESAHAVPURAM |
502 |
PREVENTIVE MAINTENANCE |
22.03.23 10:30 |
22.03.23 12:30 |
PARTS OF WZPIA |
2 |
7 |
10 |
KESAHAVPURAM |
502 |
PREVENTIVE MAINTENANCE |
22.03.23 13:30 |
22.03.23 15:30 |
PARTS OF WZPIA |
2 |
6 |
11 |
KESAHAVPURAM |
502 |
PREVENTIVE MAINTENANCE |
22.03.23 13:30 |
22.03.23 15:30 |
PARTS OF WZPIA |
2 |
7 |
12 |
KESAHAVPURAM |
509 |
PREVENTIVE MAINTENANCE |
22.03.23 10:45 |
22.03.23 12:45 |
PARTS OF WZPIA |
2 |
3 |
14 |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 13:00 |
PART OF E-2 S.PURI.. |
2 |
695 |
15 |
MANGOLPURI |
518 |
PREVENTIVE MAINTENANCE |
22.03.23 14:00 |
22.03.23 16:00 |
PART OF E-6 S.PURI.. |
2 |
244 |
16 |
MODEL TOWN |
413 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 13:00 |
PART OF BHAI PARMANAND COLONY |
2 |
295 |
17 |
MODEL TOWN |
413 |
PREVENTIVE MAINTENANCE |
22.03.23 14:00 |
22.03.23 16:00 |
PART OF BHAI PARMANAND |
2 |
170 |
18 |
MODEL TOWN |
413 |
PREVENTIVE MAINTENANCE |
22.03.23 07:00 |
22.03.23 09:00 |
1 HT CONSUMER OF DELHI JAL BOARD |
2 |
1 |
20 |
NARELA |
511 |
PROJECT WORK |
22.03.23 10:00 |
22.03.23 16:00 |
PARTS OF DJB TUBEWELL |
6 |
45 |
22 |
NARELA |
514 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 15:00 |
PART OF RAJEEV COLONY AND SANJAY COLONY |
4 |
1210 |
23 |
NARELA |
514 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 15:00 |
PART OF PREM COLONY |
4 |
610 |
24 |
NARELA |
517 |
PREVENTIVE MAINTENANCE |
22.03.23 12:00 |
22.03.23 14:00 |
PART OF BAKHTAWARPUR |
2 |
37 |
25 |
NARELA |
517 |
PROJECT WORK |
22.03.23 15:00 |
22.03.23 16:00 |
PART OF PALLA |
1 |
900 |
26 |
NARELA |
517 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 15:00 |
PART OF RENNYWELL |
4 |
51 |
28 |
PITAMPURA |
508 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 13:00 |
PART OF KP BLK |
2 |
204 |
29 |
PITAMPURA |
508 |
PREVENTIVE MAINTENANCE |
22.03.23 10:30 |
22.03.23 12:30 |
PART OF MP BLK |
2 |
569 |
33 |
SHALIMARBAGH |
414 |
PREVENTIVE MAINTENANCE |
22.03.23 10:30 |
22.03.23 14:30 |
PART OF PRADHAN ENCLAVE |
4 |
1500 |
34 |
SHALIMARBAGH |
414 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 15:00 |
PART OF PRADHAN ENCLAVE |
4 |
50 |
36 |
SHALIMARBAGH |
503 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 15:30 |
PART OF BHALSWA DAIRY |
4 |
1236 |
37 |
SHALIMARBAGH |
503 |
PROJECT WORK |
22.03.23 11:00 |
22.03.23 15:30 |
PART OF KATHIYA BABA COLONY |
4 |
214 |
39 |
SHALIMARBAGH |
532 |
PREVENTIVE MAINTENANCE |
22.03.23 11:00 |
22.03.23 15:00 |
PART OF WAZIRABAD VILLAGE |
4 |
350 |